Q. The following table shows the activities and their respective duration in days

  • Draw the network diagram by using CPM,
  • Identify the various path,
  • Identify the critical path,
  • Find out EST, EFT, LST and LFT
  • Identify the floats
ActivityDurationESTEFTLSTLFT
1-250
2-33
2-42
2-51
3-64
4-86
5-75
6-87
7-82

Various Paths

1-2-3-6-8 = 19 days 1-2-4-8 = 13 days 1-2-5-7-8 = 13 days

Critical Path

The critical path is the longest path in the network

1-2-3-6-8 = 19 days

EST - Earliest Start Time

EFT - Earliest Finishing Time

LST - Latest Start Time

LFT - Latest Finishing Time